PlanningMobilisingIn progressReportingCompleteInvoiced EEHA remediation
Contract value
$96,500
$0 claimed
Hours
216 / 520
35% complete
Labour cost to date
$18,144
$29,160 at charge rates
Margin to date
37.8%
labour only
Ex items in scope
34 / 34
11 with defects
Crewneeds: Site induction / White Card · CompEx Ex01–Ex04 · WA Electrical Licence (A-grade) — checked against expiry before anyone is allocated
| Person | Role | Tickets checked | From | To | ||
|---|---|---|---|---|---|---|
| Callum Fraser | E&I Supervisor | Site induction · CompEx Ex01–Ex04 · WA Electrical Licence | 28 Sep 2026 | 30 Oct 2026 | Valid | |
| Ryan O'Neill | LV Electrician (dual trade) | Site induction · CompEx Ex01–Ex04 · WA Electrical Licence | 28 Sep 2026 | 30 Oct 2026 | Expiring | |
DefectsDefects board →
| Defect | Item | Severity | Description | Stage |
|---|---|---|---|---|
| DEF-5403 | PLU-CG-117 | P1 | Unsealed cable entry — dust ingress | Rectified |
| DEF-5405 | PLU-SO-128 | P1 | IS barrier documentation not on file | Scheduled |
| DEF-5407 | PLU-PT-138 | P1 | Ex label illegible — certification cannot be verified | Scheduled |
| DEF-5414 | PLU-GD-177 | P1 | Earth bond loose | Rectified |
| DEF-5415 | PLU-M-178 | P1 | Cable gland not suitable for protection concept — Ex e gland on Ex d enclosure | Scheduled |
| DEF-5416 | PLU-CS-181 | P1 | Gasket damaged / IP rating compromised | Scheduled |
| DEF-5418 | PLU-JB-191 | P1 | Cable gland not suitable for protection concept — Ex e gland on Ex d enclosure | Rectified |
| DEF-5411 | PLU-HT-162 | P2 | Fasteners missing on Ex d cover | Scheduled |
| DEF-5412 | PLU-PT-167 | P2 | Fasteners missing on Ex d cover | Scheduled |
| DEF-5417 | PLU-SO-185 | P2 | Fasteners missing on Ex d cover | Scheduled |
| DEF-5419 | PLU-JB-199 | P2 | Gasket damaged / IP rating compromised | Scheduled |
| DEF-5408 | PLU-M-147 | P2 | Unsealed cable entry — dust ingress | Verified |
| DEF-5409 | PLU-HT-148 | P2 | Cable gland not suitable for protection concept — Ex e gland on Ex d enclosure | Verified |
| DEF-5410 | PLU-SV-159 | P2 | Fasteners missing on Ex d cover | Verified |
| DEF-5413 | PLU-PP-174 | P2 | Missing stopping plug on unused entry | Verified |
| DEF-5404 | PLU-PP-125 | P3 | IS barrier documentation not on file | Verified |
| DEF-5406 | PLU-CG-132 | P3 | IS barrier documentation not on file | Verified |
Timesheets216 h
| Date | Person | Hours | Value | Status | |
|---|---|---|---|---|---|
| 08 Oct 2026 | Callum Fraser | 12 | $1,740 | Submitted | |
| 08 Oct 2026 | Ryan O'Neill | 12 | $1,500 | Submitted | |
| 07 Oct 2026 | Callum Fraser | 12 | $1,740 | Submitted | |
| 07 Oct 2026 | Ryan O'Neill | 12 | $1,500 | Submitted | |
| 06 Oct 2026 | Callum Fraser | 12 | $1,740 | Submitted | |
| 06 Oct 2026 | Ryan O'Neill | 12 | $1,500 | Submitted | |
| 05 Oct 2026 | Callum Fraser | 12 | $1,740 | Submitted | |
| 05 Oct 2026 | Ryan O'Neill | 12 | $1,500 | Submitted | |
| 02 Oct 2026 | Callum Fraser | 12 | $1,740 | Approved | |
| 02 Oct 2026 | Ryan O'Neill | 12 | $1,500 | Approved | |
| 01 Oct 2026 | Callum Fraser | 12 | $1,740 | Approved | |
| 01 Oct 2026 | Ryan O'Neill | 12 | $1,500 | Approved | |
| 30 Sep 2026 | Callum Fraser | 12 | $1,740 | Approved | |
| 30 Sep 2026 | Ryan O'Neill | 12 | $1,500 | Approved | |
| 29 Sep 2026 | Callum Fraser | 12 | $1,740 | Approved | |
| 29 Sep 2026 | Ryan O'Neill | 12 | $1,500 | Approved | |
| 28 Sep 2026 | Callum Fraser | 12 | $1,740 | Approved | |
| 28 Sep 2026 | Ryan O'Neill | 12 | $1,500 | Approved | |
- Client
- Woodside Energy
- Site
- Pluto LNG — Train 1 utilitiesBurrup Road, Burrup WA 6714
- Lead
- Callum Fraser
- Dates
- 28 Sep 2026 – 30 Oct 2026
- Client PO
- 4510882716
Access: Client induction and permit to work.
Claims$0 / $96,500
No claims yet. Approved timesheets invoice from Timesheets; Invoiced raises the final claim.