Lines72 labour hours · pick from the rate card or type your own
| Type | Description | Qty | Unit | Rate | Total | Margin | |
|---|---|---|---|---|---|---|---|
| Labour | LV electrician (A-grade) | 64 | hr | $118.00 | $7,552.00 | 39.0% | |
| Labour | E&I supervisor | 8 | hr | $145.00 | $1,160.00 | 40.7% | |
| Materials | Emergency luminaires, cable & containment | 2 | lot | $850.00 | $1,700.00 | 38.8% | |
E&I constructionSent
- Client
- Water Corporation
- Site
- Woodman Point WWTP — switchroom
- Attention
- Michael Tran
- Prepared by
- Tayla Le Quesne
- Date
- 01 Oct 2026
- Valid until
- 15 Nov 2026
Cost$6,336.00 Sell (ex GST)$10,412.00 GST$1,041.20 Total inc GST$11,453.20
Margin 39.1% $4,076
Haztech Solutions Pty Ltd
18 Carbon Court, Osborne Park WA 6017 · (08) 6268 0486 · accounts@haztechsolutions.com.au
ABN 48 612 507 333
Estimate
HE-26-0147
Date 01 Oct 2026
Valid until 15 Nov 2026
Prepared by Tayla Le Quesne
Estimate to
Water Corporation
Attn: Michael Tran
Site: Woodman Point WWTP — switchroom
629 Newcastle Street, Leederville WA 6007
ABN 28 003 434 917
E&I construction
Variation — additional emergency lighting circuits| Description | Qty | Rate | Amount |
|---|---|---|---|
| LV electrician (A-grade) | 64 hr | $118.00 | $7,552.00 |
| E&I supervisor | 8 hr | $145.00 | $1,160.00 |
| Emergency luminaires, cable & containment | 2 lot | $850.00 | $1,700.00 |
| Subtotal (ex GST) | $10,412.00 |
| GST 10% | $1,041.20 |
| Total (inc GST) | $11,453.20 |
Rates ex GST. Labour charged on timesheets at the rates shown; travel and LAHA at cost plus margin. Electrical work under WA EC012708 / VIC REC 37434. Estimate valid for 45 days.
Electrical & Instrumentation · Hazardous Area (EEHA) · White-Collar Secondment · WA EC012708 · VIC REC 37434