Haztech Solutions

HE-26-0141

Burrup LNG Operations — 3-yearly detailed inspection — Compressor Station 2 (640 Ex items)
Demo 09 Oct 2026
← Estimates From ENQ-26-0162
Lines920 labour hours · pick from the rate card or type your own
TypeDescriptionQtyUnitRateTotalMargin
Labour EEHA lead inspector 200 hr $155.00 $31,000.00 43.2%
Labour EEHA inspector (CompEx) 680 hr $135.00 $91,800.00 42.2%
Labour EEHA engineer — defect review & dossier update 40 hr $185.00 $7,400.00 41.6%
Travel FIFO flights Perth–site return (per person) 6 ea $1,250.00 $7,500.00 21.6%
Travel Living away allowance (per person per night) 84 night $180.00 $15,120.00 16.7%
Equipment RFID tag & register entry (per Ex item) 640 item $6.00 $3,840.00 63.3%
Equipment Test equipment & IR tester hire (per week) 4 wk $650.00 $2,600.00 53.8%
Report Verification dossier compilation & sign-off 1 ea $4,500.00 $4,500.00 53.3%
EEHA inspectionSent
Client
Burrup LNG Operations
Site
Burrup LNG — Compressor Station 2
Attention
Glen Hutchins
Prepared by
Tayla Le Quesne
Date
24 Sep 2026
Valid until
08 Nov 2026
Cost$98,148.00 Sell (ex GST)$163,760.00 GST$16,376.00 Total inc GST$180,136.00
Margin 40.1% $65,612
Scope
Inspection to AS/NZS 60079.17. Two-person crew, 2 × 14-day swings. Defects reported in the register with photos; remediation quoted separately.
Haztech Solutions
Haztech Solutions Pty Ltd
18 Carbon Court, Osborne Park WA 6017 · (08) 6268 0486 · accounts@haztechsolutions.com.au
ABN 48 612 507 333
Estimate
HE-26-0141
Date 24 Sep 2026
Valid until 08 Nov 2026
Prepared by Tayla Le Quesne
Estimate to
Burrup LNG Operations
Attn: Glen Hutchins
Site: Burrup LNG — Compressor Station 2
Burrup Peninsula, Karratha WA 6714
ABN 92 107 664 381
EEHA inspection
3-yearly detailed inspection — Compressor Station 2 (640 Ex items)
DescriptionQtyRateAmount
EEHA lead inspector200 hr$155.00$31,000.00
EEHA inspector (CompEx)680 hr$135.00$91,800.00
EEHA engineer — defect review & dossier update40 hr$185.00$7,400.00
FIFO flights Perth–site return (per person)6 ea$1,250.00$7,500.00
Living away allowance (per person per night)84 night$180.00$15,120.00
RFID tag & register entry (per Ex item)640 item$6.00$3,840.00
Test equipment & IR tester hire (per week)4 wk$650.00$2,600.00
Verification dossier compilation & sign-off1 ea$4,500.00$4,500.00
Subtotal (ex GST)$163,760.00
GST 10%$16,376.00
Total (inc GST)$180,136.00
Inspection to AS/NZS 60079.17. Two-person crew, 2 × 14-day swings. Defects reported in the register with photos; remediation quoted separately. Rates ex GST. Labour charged on timesheets at the rates shown; travel and LAHA at cost plus margin. Electrical work under WA EC012708 / VIC REC 37434. Estimate valid for 45 days.
Electrical & Instrumentation · Hazardous Area (EEHA) · White-Collar Secondment · WA EC012708 · VIC REC 37434